Trombay plant's 500 MW unit modernisation by 2015: Tata Power

Tata Power expects to complete modernisation work of one of the 500 MW units at its long-running Trombay

thermal plant, that would allow use of coal as a fuel for electricity generation, by early 2015.

The decision to modernise the 500 MW unit came in the wake of gas shortages and higher oil prices that has led

to under utilisation of the installed generation capacity.

This 500 MW unit -- which can now run only on oil and gas -- is part of the total 1,580 MW installed capacity

at the Trombay thermal plant that supplies power to Mumbai.

"We see costs of oil and gas rising and thus have proposed modernisation which will help reduce costs and

ensure higher utilisation of capacity," Tata Power Executive Director S Padmanabhan told PTI in an e-mailed

statement.

According to Tata Power, the modernisation work -- of unit 6, having 500 MW capacity -- is expected to be

complete by early 2015. The country's largest private power producer would invest Rs 1,174 crore toward

modernisation, that would allow the use of coal to generate power from the unit.

"The dire need for modernisation has risen due to unavailability of natural gas which has resulted in Tata

Power being dependent on expensive fuel like oil to run its unit 6," the statement said.

Further, a shortage of low sulphur oil from local refineries and spiralling prices of imported oil and gas have

led to significant escalation in the absolute cost of power generation from unit 6, it added.

As a result, the unit's Plant Load Factor (PLF) -- a measure of operational efficiency -- is around 50 per

cent. "This has necessitated modernisation, thus ensuring additional option of coal firing for optimum

utilisation of the existing power generation infrastructure...," Tata Power said.

Tata Power said the modernisation would help in utilising the full capacity of 500 MW at best operating

efficiency besides reducing "fuel cost and thus help lower tariffs for Mumbai customers".

It includes addition of the latest state-of-the-art coal firing equipment and installation of pollution control

equipment to make the unit work on coal, oil and gas, wherein all three fuels can be combined in any

percentage.

The Trombay plant, which began operations way back in 1956, currently has five units. Unit 5 and 6 have 500 MW

capacity each, while unit 4 has 150 MW, unit 7 (180 MW) and unit 8 (250 MW).

Tata Power has an installed generation capacity of 6,899 MW.

 

https://economictimes.indiatimes.com/news/news-by-industry/energy/power/trombay-plants-500-mw-unit-modernisation

-by-2015-tata-power/articleshow/17635407.cms
 

Join Asian Power community
Since you're here...

...there are many ways you can work with us to advertise your company and connect to your customers. Our team can help you dight and create an advertising campaign, in print and digital, on this website and in print magazine.

We can also organize a real life or digital event for you and find thought leader speakers as well as industry leaders, who could be your potential partners, to join the event. We also run some awards programmes which give you an opportunity to be recognized for your achievements during the year and you can join this as a participant or a sponsor.

Let us help you drive your business forward with a good partnership!