Pacific Blue to build 60 MW battery system in South Australia

The project’s construction will cost over $66.3m.

Pacific Blue will be constructing a 60-megawatt (MW) battery energy storage system (BESS) next to its existing wind farm in South Australia, expected to be completed in early 2026.

In a statement, Pacific Blue said the BESS project, which will cost over $66.3m (A$100m) to develop will have a duration of 130 MW-hours,  supporting the state to meet its 2027 renewable targets.

“The focus of Australia’s energy transition so far has overwhelmingly been on the generation of renewable energy – storing that energy and deploying it to support grid stability is the missing piece and a critical component of Australia’s renewable energy transition,” Pacific Blue CEO Domenic Capomolla.

“The construction of Clements Gap BESS is the first key milestone for Pacific Blue in realising our 2-gigawatt pipeline of capacity and energy storage solutions, which will contribute to Australia achieving net zero carbon emissions by 2050,” he added.

The company, the only 100% renewable energy generator and retailer in Australia, has a total installed capacity of 665 MW of wind, hydro, and solar assets.

$1 = A$1.51

Join Asian Power community
Since you're here...

...there are many ways you can work with us to advertise your company and connect to your customers. Our team can help you dight and create an advertising campaign, in print and digital, on this website and in print magazine.

We can also organize a real life or digital event for you and find thought leader speakers as well as industry leaders, who could be your potential partners, to join the event. We also run some awards programmes which give you an opportunity to be recognized for your achievements during the year and you can join this as a participant or a sponsor.

Let us help you drive your business forward with a good partnership!

Edit Node Button Block

This block is broken or missing. You may be missing content or you might need to enable the original module.