Kaifeng’s 2×600MW units ready for power generation

Kaifeng Power Plant’s extension project passed the 168-hour test run with a 100 percent rate in automation, protection, instrument startup and steam-water quality. The successful test run signals its completion for generation.

The extension project, with an average load of 100.83 percent, includes two 600MW units.

The period for its completion of only 17 months and 17 days is a benchmark for construction schedule in China, according to the China Power Investment Corporation.

Unit 1 of the plant was put into operation on 17 December 2008.

The completion will play a profound role in further optimising the power structure of the China Power Investment Corporation and Henan province, saving resources and promoting the economic development of Kaifeng and eastern Henan.

Join Asian Power community
Since you're here...

...there are many ways you can work with us to advertise your company and connect to your customers. Our team can help you dight and create an advertising campaign, in print and digital, on this website and in print magazine.

We can also organize a real life or digital event for you and find thought leader speakers as well as industry leaders, who could be your potential partners, to join the event. We also run some awards programmes which give you an opportunity to be recognized for your achievements during the year and you can join this as a participant or a sponsor.

Let us help you drive your business forward with a good partnership!