A-Power inks new project with Handan Fengfeng
A-Power signed a US$16.4million engineering, procurement, and construction contract with Handan Fengfeng for a power generation project.
The project includes a 75 metric ton coke oven gas boiler, and a 15MW condensing steam turbine generator driven by the coke oven gas boiler. Work on the project started in December 2010 and is expected to last 10 months.
"We are very pleased to have been selected for this project which is our third project for Handan Fengfeng. We view this not only as recognition of our capabilities but also of the quality of our work on earlier projects," said Mr. Jinxiang Lu, A-Power's Chairman and CEO.