NHPC project gets delayed again due to BHEL's sluggishness

The chances of NHPC commissioning the Nimoo Bazgo hydroelectric project on the revised schedule appeared increasingly bleak after BHEL delayed milestones.

 

The power house concreting, which has been delayed repeatedly over the past few months, has witnessed no progress during the previous month.

Currently, 3,208 cum of concreting, out of the cumulative 23,000 cum, remains to be concluded. In contrast to this, the dam works have advanced much more than the projected target for the month of December 2011.
 
Although 500 cum was scheduled to be laid out for left side non overflow blocks for the month of December, Bharat Heavy Electricals Limited has managed to achieve 600 cum, thereby bringing the cumulative work concluded up to 12,485 cum, out of the total of 42,800 cum.

To note, the 45 MW project is a run-of-river scheme, planned to harness the hydropower potential of the Indus river, in the Leh district of the state. It envisages the construction of a 57 m high concrete gravity dam, three 6.3 m long penstocks, with a diameter of 3.3 m, each, and a surface power house with four Francis turbine units of 15 MW capacity, each. The project would afford an annual energy generation of 239 million units, assuming 90% performance.

Follow the link for more news on

Join Asian Power community
Since you're here...

...there are many ways you can work with us to advertise your company and connect to your customers. Our team can help you dight and create an advertising campaign, in print and digital, on this website and in print magazine.

We can also organize a real life or digital event for you and find thought leader speakers as well as industry leaders, who could be your potential partners, to join the event. We also run some awards programmes which give you an opportunity to be recognized for your achievements during the year and you can join this as a participant or a sponsor.

Let us help you drive your business forward with a good partnership!