Dalian Wind Farm starts operation
Northeast New Energy Company's 49.5MW project covering Phase 1 of Dalian Tuoshan Wind Farm successfully began generation.
Commenced in August 2008, the Tuoshan Wind Farm Phase I has overcome such difficulties as unsmooth land claim, bad geological conditions, difficult conditions for construction to complete the installation of all 33 wind turbines on 23 September 2009.
During the commissioning period, a cold wave broke out and temperature dropped sharply. All staff of Tuoshan Wind Farm and technicians of many equipment providers and construction contractors made strenuous concerted efforts to ensure the smooth commissioning.
So far, Northeast New Energy Company has accomplished the goal of putting three projects into operation recently, including Beipiao Beitazi, Chifeng Yihegong and Dalian Tuoshan.