Our customers are facing a challenging future. They want a flexible and viable partner to support them in a world of changing expectations. EthosEnergy turns on potential to deliver services and solutions globally for rotating equipment to make energy affordable, available and sustainable. A unique combination of partnership and service quality, backed by a track record of tailored solutions, for the power, oil & gas, industrial and aerospace markets. EthosEnergy operates in over 100 countries to consistently improve performance across the value chain.

Chlorine compressor upgrade

A large chemical company contacted our Hengelo, Netherlands operation for a new titanium impeller for a chlorine compressor and upgrade.

Goals

  • Reduce Maintenance Spend
  • Increase Power Output
  • Life Extension

Sectors

  • Power generation

Asset

  • Compressors

Location

  • Hengelo , Netherlands

 2.6kg

Reduced impeller weight by 2.6kg

 20 years

This unit was running with high vibrations and a strange response to the daily water wash cycles for over 20 years.

Less water wash cycles

The customer can now run the compressor in a stable mode with less water wash cycles.

Project Overview

A large chemical company contacted our Hengelo, Netherlands operation for a new titanium impeller for a chlorine compressor and upgrade. This unit was running with high vibrations and a strange response to the daily water wash cycles for over 20 years. Sometimes the vibration would drop after a water wash, and sometimes the vibration would increase after water wash cycles.

Key Challenges

  • EthosEnergy specialists performed a vibration measurement on-site followed by a complete rotordynamic analysis
  • The rotor meets the API 617 requirements
  • A synchronous rotor instability analysis was executed for this compression rotor (Morton Effect)
  • The synchronous rotor instability analysis confirmed the expectation that the compressor operating speed (9,930 rpm) is close to the onset on instability and explained the high sensitivity of the rotor to impeller imbalance

Project Highlights

  • Reduce the overhang movements (impeller weight)
  • Reduce the differential temperature across the bearing

Overweight and unstable

Rotordynamic analysis confirmed the impeller is overweight and unstable

2.6kg

Reduced impeller weight by 2.6kg

Titanium impeller

Manufactured a titanium impeller

Key Results

After the impeller reversal and redesign, EthosEnergy started the manufacturing process of the titanium impeller. Furthermore, the customer can now run the compressor in a stable mode with less water wash cycles.

2.6 kg

EthosEnergy was able to reduce the impeller weight by 2.6 kg by reducing the vane width, added balancing holes, & a redesign of the impeller lock nut by carving out the back side of the impeller hub.

Connect Now

CAPTCHA
This question is for testing whether or not you are a human visitor and to prevent automated spam submissions.

Other Articles

What future-proofing looks like for the energy market

EthosEnergy’s suite of life extension and emissions compliance solutions aims to make energy affordable, available, and sustainable for its clients.

EthosEnergy nominated for Optimisation Award at the EIC Awards 2022

EthosEnergy has been shortlisted for the Optimisation category in the Energy Industries Council (EIC) Awards 2022, which recognizes companies who focus on improving internal decision-making, costs, processes, agility, structures, and enhancing competitiveness.

Geothermal steam turbine retrofit

Due to the continued steam decline of the geothermal reservoir, the single operating turbine at Tiwi Geothermal Plant (TGP) operated at approximately half capacity and resulted in inefficient steam consumption.

Gas turbine rotor overhaul

EthosEnergy was contracted to provide gas turbine rotor overhaul for a European refinery.

Reduced outage and costs on a D-11 steam turbine

Patented leading edge restoration process on L-0 titanium blades for a D-11 steam turbine for a large utility company in the southeast US. 

Turnkey water injection upgrade on frame 9EA units

A simple-cycle peaking facility in the arid desert of northern Chile was facing strict emissions regulations that required modifications to their two Frame 9EA, 126 MW Gas Turbines

EthosEnergy promotes innovative and sustainable solutions for the energy industry in Israel

One of the significant trends in the formulation of Israel's energy policy is the adoption of a circular model that offers efficient use of resources in industrial plants and power plants, to slow down the effects of the climate crisis and accelerate the transition to sustainable energy.

EthosEnergy Union Field Services wins silver at Safety Excellence Awards

EthosEnergy Union Field Service team from the Gulf Coast was awarded the silver award for Safety Excellence at the 35th annual Houston Safety Excellence Awards Gala.

EthosEnergy awarded multi-million dollar operations and maintenance contract extension by TexGen Power

Houston, TX – EthosEnergy has secured a multi-million dollar operations and maintenance (O&M) contract extension by TexGen Power for the operation of three power generation assets in Texas.

EthosEnergy Announces Patricia Gonzalez as Executive Vice President, West Hemisphere

Houston, TX – EthosEnergy, a global independent service provider for critical rotating equipment, announces the appointment of Patricia Gonzalez as Executive Vice President for the West Hemisphere.

EthosEnergy Keeps Telfer Site Operational During Cyclone

Telfer, Australia – On Thursday, April 13, the Western Australian coast witnessed Isla, a Category 5 cyclone which left the Telfer mine in its direct path. The site was predicted to receive the force of a Category 3 cyclone around midday on April 14, leaving the site owners, Newcrest, with a difficult decision to make.

EthosEnergy Appoints Former ItalPresseGauss CEO, Mario Cincotta as New East Hemisphere Executive Vice President

Aberdeen, United Kingdom--(Newsfile Corp. - March 14, 2023) - EthosEnergy has appointed Mario Cincotta, former CEO of ItalPresseGauss and Senior Vice President of Norican Group, as its new Executive Vice President of East Hemisphere. Mario will have strategic and operational leadership for the East Hemisphere. He will be based in Italy and report into the CEO, Ana Amicarella.